Basement is 3/4 done. It's time for us to finish it... whoa!
We need to do the perimeter insulation, we need to decide on the company who will deliver and install the basement windows, we need to finalize the electricity, gas, telephone and cable installation, we need to order the remaining needed materials to fully finish the basement, we need to coordinate with our earthworks company for filling-in the sides of the basement, we need to have electrical plan for the basement and many more.
We didn't start our part yet until now since hubby have projects out-of-town. We need to wait until weekends or atleast when hubby got his vacation leave. I was able to get the schedule of the on-site meeting with E-ON Mitte (electricity, gas and telecom) as well as with ZMW (in charge of the water installation). It is scheduled first week of October. Too bad that their earthworks people are not available next week. It was originally scheduled on Monday.
We also received a lot of bills today. I guess we will be bombarded with bills in the next weeks, yay! That means we need to prepare the necessary papers with supporting documents and pictures to send out to the bank. I am still scared about the bill of our earthwork company. I guess I will collapse when we receive it.
In the meantime, we are waiting for the call of our Architect for the Basement's Site Acceptance Test. This is important before we will start the perimeter insulation.
Oh and by the way, hubby got his first snail mail addressed to our future residence.. it was from the EON Mitte ha ha.