Friday, March 14, 2014

Joints Fan for Bricks (Fugenlüfter)

We put the joints fan for our bricks.

During the brick installation, there were holes specially made for the bricks to have possible air circulation in between the wall and the bricks. On these holes, we are going to put joints fan or Fugenlüfter as they call it here. This is to prevent bees, wasps or even mouse to get-in or build their house in between the bricks and the wall.

This is how it looks like:


We installed few of it on the bricks and this is how it looks like:




Monday, February 24, 2014

Bricks Installation Day 5 (Klinker Montage Tag 5)

I went today in the building site to check on the bricklayers. Normal schedule is that they are going to continue and finish the brick laying today. They mentioned that they will be finished at 11 am. I brought coffee for them. I also put back some insulation materials on the walls and ceilings that hubby needs to take-off during the electric cables intallation. At around 11 am, they were really finished. They were just cleaning-up around and disabling the scaffolding. Before they left, the leader of the troop read and let us sign the documents stating that everything was delivered, properly installed, the building site was left clean and no major damages made on the building site/house. This is how our house looks like now...








Thursday, February 20, 2014

Bricks Installation Day 4 (Klinker Montage Tag 4)

Weather : The streets are still wet from the rain yesterday, but as of this morning at around 10:15 am it did not rain at all.

Today the bricklayers will be driving back home (4 hrs drive from our place). The head of the troop mentioned that they are driving this afternoon. They will be back on Monday to finish the job.











In the afternoon...










Wednesday, February 19, 2014

Bricks Installation Day 3 (Klinker Montage Tag 3)

The weather is not so good because it is raining. It is not hard but still raindrops are falling on my head. The leader of the bricklayers troop mentioned that they will not be able to finish it this week, but probably on Monday. Hopefully the weather will not mess it up.




Til noon time...











In the afternoon, this is how it looks like...











Tuesday, February 18, 2014

Bricks Installation Day 2 (Klinker Montage Tag 2)

The stress is getting more and more each day. I did not thought that bricks installation will be this stressful for me. It is the same like dealing with the an open contract, just in a different point of view. Anyway, I WISH it will be finished soon and it will give us a good result.

The bricklayer troop are working good, fast and on time. The only issue is on our end. The lower portions of the two long thin windows that we have, the terraces doors and the main entrance are still open or not yet installed with bricks.




At noon time, this is how it looks like...





In the afternoon...