Wednesday, April 30, 2014

Heating System Installation Part 2 (Heizungsinstallation Teil 2)

Our heating system specialist (Starkon) with his helper arrived at 10:45 am at the building site today. Around 11:00 am the head of the team fetched some materials and then was back at 11:20 am.

The goal for this day is to finish the heating system installation, double check on the solar (if everything is working good), before we will close the ceiling part of one the rooms where the pipe is running thru.

The heating system specialist and his team left the building site at around 13:15 pm.




Tuesday, March 25, 2014

Heating System Installation Part 1 (Heizungsinstallation Teil 1)

Our heating system specialist and his helpers arrived at 9:15 am at the building site. They started the set-up / installation of our heating system. They worked til 4pm.






Sunday, March 23, 2014

Laying the Copper Pipe Part 2 (Kupferrohr verlegen Teil 2)

We layed the second copper pipe for our solar collector.

Since this work needs at least three people eventhough it's Sunday, FIL went to the building site and helped us.




Saturday, March 15, 2014

Laying the Copper Pipe Part 1 (Kupferrohr verlegen Teil 1)

The three of us (FIL, hubby and I) went to the building site today to lay the copper pipe for our solar collector. This can easily be bent and destroyed, therefore, we need to lay it with extra care. We lay it from the attic until the basement. We also put the protection for the copper pipe.

The heating specialist will do the installation hopefully in a week or two. We need to meet him on Monday for the plan. We prepared the copper pipe, so the heating installation process will not waste any time, it will be less work needed for the specialist and less costs on our end :)


Friday, November 8, 2013

Heating System Consultant and Installer's Visit

Today we met Herr W. who will do our heating system. He checked on the house, where the pipes will go thru, how and where the Solar panel will be installed, he also checked the equipments delivered to fully install the heating system. There are two things that are not OK, but as of the moment, everything is fine.

We made a schedule to install the solar panel for Tuesday next week. I hope the weather will cooperate. This is important, because the scaffolding is still around the house.