For recap, we applied for the building permit last July. ProHaus Architect's Office prepared a wrong application form. Engineer from the Regional Office, Herr S, (who's in-charge of building permits in the area), was on vacation leave during the time our application arrived on their deparment. We waited for three weeks before we learned that we should have applied for building permit under paragraph 56 of HBO. A lot of time wasted *sigh*
We changed the application form to building permit under paragraph 56 last August 26. We completed the attached documents (papers that we sent to Engineer's Regional Office and was returned to us), last August 28.
It is very frustrating to encounter such situation. We just lost time bcoz of nothing. And to think... when building a house, time is not only gold, but it is also costing money :(
Update: Hubby went to the City Hall before directly driving to office just to fix this issue. Good that he did that. Now we learned that it is ok to continue. From City Hall's Engineer's Office, there is no problem about the application.
Update: Hubby went to the City Hall before directly driving to office just to fix this issue. Good that he did that. Now we learned that it is ok to continue. From City Hall's Engineer's Office, there is no problem about the application.