Basement Plan Arrived (Kellerplan)

Today, we received the basement plan (Kellerplan) from ProHaus. This is the workplan that will be followed by the people who are going to build our basement. Our tentative schedule in building the basement is on the 38th week. But before that, we need to have our Building Permit (Baugenehmigung) first.

Talking about Building Permit, the person-in-charge who is working on our application called today and said that we should have sent a different application (§ 56 HBO), so the process will not be too long (atleast two weeks) and not too expensive (normally it costs around 1,500+€). We received this feedback after a month of our application. So many wasted times and is really frustrating. Now, we need to contact our CAD from ProHaus to ask her assistance regarding this. I hope everything will still be all possible.