Wednesday, September 10, 2014
Filling-in the Plasterboard of the Living and Dinning Room Walls (Verspachteln Gipskartonplatten WohnEssbereich)
Hubby's dad started filling-in the plasterboard of the living and dinning room while hubby and I worked on the kitchen area.
Drywall Installation Living and Dinning Room 2 (Rigips Installation WohnEssbereich Teil 2)
Hubby and his dad installed the drywall on other two sides of our living and dinning room. Now, it is looking better :)
Tuesday, September 9, 2014
Ceiling Substructure Living and Dinning Room (Deckenunterkonstruktion WohnEssbereich)
It has been awhile since we last worked on the ceiling substructure of our house. I am excited to see it being done in our groundfloor. For sure it will look different, and it will again add HOPE that our house will be finish soon.
I am already happy if we will have our floor screed this year (crossing my fingers).
Hubby and I started early this Monday morning to work on the ceiling substructure in our living and dinning area. The first day was not that easy, but today we finished it.
I am already happy if we will have our floor screed this year (crossing my fingers).
Hubby and I started early this Monday morning to work on the ceiling substructure in our living and dinning area. The first day was not that easy, but today we finished it.
Saturday, September 6, 2014
Electric Works Groundfloor (Elektroarbeiten EG)
This weekend our Electrician worked for some hours. He installed the sockets and lighting in our groundfloor.
After that, hubby tested a set of light switch on one of our walls. It looks really good =) I bet it looks better when we are finish with the walls.
Friday, September 5, 2014
Clean-Up (Aufräumen)
Starting to clean-up the basement. First work is to fix the big boxes. We plan to drive it to the garbage disposal area next week.
We should slowly clean-up our basement area, so hubby can start the electric installation, we can prepare for the installation of our under floor heating, and then if we have luck, we will have our floor screed before the winter season arrives.
----
Sunday, I finished packing the boxes and it is now really for transportation.
Thursday, September 4, 2014
Painting the Canopy Foundation (Antrich Vordach Balken)
Hubby's dad painted today the canopy foundation of our house. The past few weeks were not dry, but the last few days were sunny.
Tuesday, September 2, 2014
Vapor Retarder Installation Living Room Windows (Dampfbremsefolie Installation Wohnzimmer Fenstern)
It was my first mornings that I was able to go to the building site without worrying about the kids. This is the second day that our youngest attended the Kindergarten. I then decided to do the vapor retarder installation on the lower portion of the windows.